When you change the due date of a task, you can choose to notify the assignees about this change. By doing so, you can make sure that they prioritize their work properly and deliver it on time.
  
 
	 -  
		  Go to 
			  click the name of the appropriate project, and then select the tasks whose due date you want to change. 
		   
		
-  
		  Select 
			  
		   
		
-  
		  In the 
			 Change Task And Step Due Dates dialog box, select 
			 Set Expected Duration or 
			 Set Due Date, and then enter the expected duration of the tasks or task steps (in days or hours) or their due dates (by clicking the calendar icon). 
		   
		   
			 Tip: You can set the expected duration or the due date for the tasks themselves or for each task step. 
			  
 
-  
		  Optional: If you changed one or more due dates in the 
			 Change Task And Step Due Dates dialog box, you can also select the 
			 Send email to assignees check box to make sure that assignees receive an automatic email message with the updated due date. 
		   
		   
			 Important: For the email messages to be delivered, ask your 
				 WorldServer administrator to make sure that: 
				  
				  - The assignees have valid email addresses. 
				  
- Notification delivery () is configured properly for your environment. 
				  
- The notification engine is enabled on your environment (notification_engine=on in the 
					 general.properties file). 
				  
 Administrators can also change the content of the automatic email message by going to 
				   and selecting 
				  Task Due Date Changed or 
				  Task Step Due Date Changed in the 
				  Notification Type list. 
				 
 
 
-  
		  Click 
			 OK.