Move Task - Step 2

You can move tasks to another project with the same locale or to a new project. Depending on whether you choose to move the tasks to an existing project or to a new project, you either select the existing project, or specify a name, description, and workgroup for the new project

  1. From the task view, check the task to be moved.
  2. Click More Options > Task Options > Move Task.
    WorldServer displays the Move Tasks dialog box.
  3. Choose whether to move the task to an existing project or a new project, and click Next.
  4. If you chose to move the task to an existing project, choose the project from the drop-down list and click Finish.
  5. If you chose to move the task to a new project, specify a new project name, description and workgroup for the project. Click Finish.